A5 Towcester High Street - Essential Maintenance Work
Please be aware of road closures through Towcester between July - October 2018.
Although
there are no works planned for the road area outside Parker Kitchens it
will affect the surrounding roads and your travel time to visit us.
The A5 through Towcester will be closed in sections
for 24 hours/day - follow diversions.
The following is an
estimate of the works to be carried out:
Phase 1: Tescos - Northampton Road, closed for 24 hrs for 3 weeks
Phase 2: The High street will then be closed for 24 hrs for 5 weeks
Phase 3: Richmond Road - Reffield Close, closed 24 hrs for 8 weeks
Phase 4: Up to Marlow Road, closed 24 hrs for 2 days
Phase 5: 100m from Reffield Road, closed for 1 week
For more information